🇦🇺Australia

Hohe Nacharbeitskosten wegen unzureichender Werksabnahme (FAT)

5 verified sources

Definition

Factory acceptance testing is explicitly promoted as the most cost‑effective way to ensure equipment performs correctly and meets contractual requirements before delivery, avoiding issues at the client’s site.[1][2][3] FAT providers in Australia emphasise that verifying functionality, safety, documentation and contractual specifications at the factory prevents later disputes and costly on‑site rectification.[1][4][9] When acceptance and commissioning are handled informally, defects such as missing functions, control logic errors, or incomplete manuals are discovered only during site acceptance or early operation. At that stage, manufacturers incur extra engineering hours, travel to remote Australian sites, re‑fabrication of parts and schedule‑related penalties.

Key Findings

  • Financial Impact: Quantified (Logic): Industry examples for process and packaging lines show that fixing design or integration issues at site can cost 3–5x more than at factory. For a AUD 2,000,000 line, a 3% rework impact detected only after commissioning equals ~AUD 60,000 in additional costs (engineering travel, overtime, parts). Across 3–5 major projects per year with similar issues, this can reach AUD 180,000–300,000 annually in avoidable quality failure costs.
  • Frequency: Frequent when projects are customised, schedules are tight, and customers or third‑party inspectors are not fully involved in FAT, leading to incomplete test coverage.[2][3]
  • Root Cause: Insufficient planning and scope definition for FAT; lack of structured checklists and pass/fail criteria; limited customer participation; inadequate documentation of tests and deviations; commissioning rushed to meet delivery dates, so non‑conformities are deferred to site.

Why This Matters

The Pitch: Industrial machinery manufacturers in Australia 🇦🇺 lose AUD 100,000–300,000 per year on rework, on‑site fixes and liquidated damages because issues are discovered after installation instead of during structured FAT and commissioning. Automated test planning, checklists and data capture at FAT can cut these costs by 30–50%.

Affected Stakeholders

Head of Engineering, Quality Manager, Service & Commissioning Manager, Project Manager, Operations Director

Deep Analysis (Premium)

Financial Impact

Financial data and detailed analysis available with full access. Unlock to see exact figures, evidence sources, and actionable insights.

Unlock to reveal

Current Workarounds

Financial data and detailed analysis available with full access. Unlock to see exact figures, evidence sources, and actionable insights.

Unlock to reveal

Get Solutions for This Problem

Full report with actionable solutions

$99$39
  • Solutions for this specific pain
  • Solutions for all 15 industry pains
  • Where to find first clients
  • Pricing & launch costs
Get Solutions Report

Methodology & Sources

Data collected via OSINT from regulatory filings, industry audits, and verified case studies.

Evidence Sources:

Related Business Risks

Verzögerte Rechnungsstellung durch verspätete Abnahmeprotokolle

Quantified (Logic): On a typical AUD 2,000,000 machinery project with 10% retention and a 30% commissioning milestone (AUD 800,000 tied to acceptance), a 45‑day delay in customer sign‑off at a 8–10% annual cost of capital costs ~AUD 8,000–10,000 in financing charges per project. With 5–10 such projects per year, this equates to AUD 40,000–100,000 annually in avoidable time‑to‑cash drag.

Verlorene Mehrerlöse durch nicht abgerechnete Zusatzleistungen bei Inbetriebnahme

Quantified (Logic): On a AUD 2,000,000 custom machinery contract, it is typical for commissioning‑phase variations and additional services (software changes, extra tests, operator training) to equate to 2–4% of contract value if fully costed, i.e. AUD 40,000–80,000 per project. If only half of these are formally captured and billed, the remaining unbilled extras represent AUD 20,000–40,000 revenue leakage per project. Across 5 projects annually, this is AUD 100,000–200,000 of lost revenue.

Verlust von Produktionskapazität durch verlängerte Inbetriebnahme beim Kunden

Quantified (Logic): Consider a food or packaging line designed to generate contribution margin of AUD 20,000–40,000 per production day once fully ramped. If commissioning and final acceptance at the customer site take 10 extra days beyond plan due to unresolved issues, the customer foregoes AUD 200,000–400,000 in margin. For the OEM, such schedule slippage often results in negotiation of discounts or free spare parts worth 1–2% of project value (~AUD 20,000–40,000 on a AUD 2,000,000 line) to resolve disputes, plus reputational damage.

Rush Order Cost Overruns

AUD 20-50% premium on rush orders; 10-20 hours/month manual expediting

Procurement Compliance Fines

AUD 10,000+ per non-compliant procurement over threshold; 20-40 hours/month manual compliance checks

Manual Procurement Bottlenecks

AUD 5,000-10,000/week idle equipment; 2-5% capacity loss

Request Deep Analysis

🇦🇺 Be first to access this market's intelligence