Unnecessary Coal Capacity Tied Up in Permit Pipeline
Definition
As of 2023, India's Central Electricity Authority data shows 34.9 GW of coal capacity in pre-construction phase and 8 GW in active construction are not required to meet demand forecasts. These projects remain tied to the environmental clearance process, representing significant opportunity cost.[2]
Key Findings
- Financial Impact: Quantified (LOGIC estimate): ₹2-3 lakh crore in stranded project capex; ₹500-1000 crore annually in carrying costs (interest, overhead) for projects in permit queue.
- Frequency: Ongoing as of August 2023; no evidence of project kills or permit consolidation.
- Root Cause: Environmental permit process creates multi-year approval bottleneck; no mechanism to discontinue unnecessary projects early. Regulatory uncertainty prevents timely capital reallocation.
Why This Matters
The Pitch: India's coal power sector has ₹2-3 lakh crore in stranded project capital (estimated 34.9 GW × ₹600 crore/GW) held in permit limbo. Real-time permit status dashboards and early kill-decision automation reduce wasted capex allocation.
Affected Stakeholders
Chief Financial Officers / Project Finance Teams, Ministry of Coal Planning Officers, Environmental Clearance Authority (EAC) Administrators
Deep Analysis (Premium)
Financial Impact
Financial data and detailed analysis available with full access. Unlock to see exact figures, evidence sources, and actionable insights.
Current Workarounds
Financial data and detailed analysis available with full access. Unlock to see exact figures, evidence sources, and actionable insights.
Get Solutions for This Problem
Full report with actionable solutions
- Solutions for this specific pain
- Solutions for all 15 industry pains
- Where to find first clients
- Pricing & launch costs
Methodology & Sources
Data collected via OSINT from regulatory filings, industry audits, and verified case studies.
Related Business Risks
Environmental Compliance Deadline Extensions & Stranded Penalties
Unbudgeted FGD Retrofit & Emission Control Equipment Costs
अनुपालन जुर्माना - राख उपयोग लक्ष्य विफलता (Compliance Penalties - Ash Utilization Target Failure)
परिवहन लागत वहन - अनिश्चित नियामक जिम्मेदारी (Transportation Cost Burden - Uncertain Regulatory Liability)
राख बिक्री राजस्व हानि - नियामक नीति अनिश्चितता (Ash Sales Revenue Loss - Regulatory Policy Uncertainty)
राख तालाब प्रबंधन अक्षमता - संचालन बाधा (Ash Pond Management Inefficiency - Operational Bottleneck)
Request Deep Analysis
🇮🇳 Be first to access this market's intelligence